Re: Squid 3.5 release timetable

From: Alex Rousskov <rousskov_at_measurement-factory.com>
Date: Fri, 22 Aug 2014 12:02:44 -0600

On 08/21/2014 11:54 PM, Amos Jeffries wrote:
> Update:
>
> * FTP and Kerberos patches are in and building fine.
> (build farm has some internal issues clouding the state)
>
> * I am punting Bearer and Parser-NG off into 3.6 series. Some design
> decisions may take a while to resolve and re-audit.
>
> * PROXY protocol and Splice/Peek appear to be almost done with audit.
>
> So if those last two can be pushed onward this week I would like to
> branch once they are merged and the build farm gives them a mostly-blue
> pass rate.

What about the boilerplate updates? I think it would be best to do them
before branching as they are another example of simple changes affecting
a lot of files. I will try to find the time to revisit that project next
week.

Thank you,

Alex.
Received on Fri Aug 22 2014 - 18:02:50 MDT

This archive was generated by hypermail 2.2.0 : Sat Aug 23 2014 - 12:00:15 MDT